The Engineering - Land Development Division acts as the City of Roseville's lead in civil improvement plan review with an emphasis on coordinating communication and approvals between the Development Community and the various reviewing departments within the City.

Upon receipt of the City of Roseville Planning Division's discretionary approval and issuance of the project Conditions of Approval, the Developer may submit a Civil Improvement Plan Review/Permit Application, including the civil improvement plans, for their project to the Permit Center to begin review of the civil improvement plans. The civil improvement plans will be distributed to the required reviewing departments. The reviewing departments will enter their comments into a consolidated comment letter compiled by the Engineering - Land Development Division and returned to the project applicant.

Standard review time is 4 weeks for first review, 3 weeks for second review, and 2 weeks for each subsequent review.


Civil Plan Review Process: